Student Intern Review
at National Grid
Internship (1 Month+)
Electronic and Electrical Engineering
Exeter
Review Submitted: August 2026
Overall Rating
4.7 /5
The Overall Rating is the average of all the ratings given in each category. We take those individual ratings and combine them into one final score!
Overview of Role
Please give an overview of your role and what this involves on a day-to-day basis.
placing meg-test pegs at various distances to calculate ground resistance. In my second week, I sat in on customer connection work, helping assess an upgrade request and weighing the cost and timeline trade-offs between a full three-phase upgrade and a simpler single-phase addition. I finalised five SMART
objectives with my line manager, went out mapping pole and overhead line GPS locations into EMU, and reached out to arrange shadowing with the NGET drone inspection team. I also attended the IET Power Academy conference, taking part in technical talks, workshops, and networking with other engineers. Week three was more technical. I worked through Company Directives on helicopter inspections and overhead line clearances, completed a Helicopter Inspections CBT, and started both an LTspice transmission line simulation exercise and the Altium Designer PCB course. I learned how pole height and clearance calculations feed into the EMU system, and studied Low Carbon Technology (LCT) connection assessments, including G99/G100 compliance and SGI2/SGI3 generation thresholds. I spent two days on-site with an overhead line team doing pole changes and insulator work, taking part in switching, PME earthing, and helical tie installation, and I learned how ring/loop network topology, back-feeding, and field control handover work. I also requested access to CROWN and STARS and began AutoCAD training. In week four, I went to Ammanford grid in Swansea, helping apply PCMEs and danger notices, while learning how outage planning and multi-site switching coordination is managed. At Lime Street substation I went through a full protection testing session, covering CT and VT ratio/polarity checks, relay pickup and drop-off testing, distance protection, and overcurrent and earth fault protection, including helping identify a genuine test discrepancy. I also learned ring-main and back-feed theory and cable sizing constraints. Later that week, I helped with an overhead line replacement at Chagford, swapping copper for ABC aluminium cable using a winch and pulley system, and I spent the end of the week preparing my Interim Review. Week five was my Engineering Design placement. I completed the trainee tasks, using AutoCAD to design a new 33/11kV primary substation, producing layouts and a single-line diagram for "Browns Substation." I learned about transformer isolation and earth fault protection, the difference between isolators and circuit breakers, and how Neutral Earthing Resistors work. I visited Avonbank feeder road and had an in- depth session with a protection engineer covering 11kV distribution protection philosophy: fuse versus earth-type protection, split-ring radial operation, why distance and differential protection aren't used on 11kV or underground circuits, IDMT theory including curve types and grading margins, auto-reclose sequencing,
and the differences between electromechanical and digital relays. I finished the week with an overview of the Primary Network Design team and more single-line drawing work for Paulton Sub. In week six, I continued the Altium PCB course, completing a four-layer stack routing exercise, building a bill of materials, and starting a new custom PCB, while connecting the electronics concepts back to power network principles like interference and transmission-line behaviour. I helped with overhead conductor
replacement using winch and brake tensioning, completed my Interim Review, and joined pole inspections with a colleague, learning how pole condition is classified and how clearance and vegetation checks are carried out. I wrote and completed my Protection Engineering report, drawing on everything I'd learned from previous weeks and conversations with protection specialists, sent my protection report to the
protection engineer at Avonbank for validation. and had Q&A sessions with colleagues in Innovation and Project Engineering. Throughout the placement, I've focused on being proactive about my own learning,
reaching out to different teams, and building a broad picture of how National Grid's operational, design, and protection functions fit together.
Were you given much responsibility during your placement / internship?
In my second week, I sat in on customer connection work, helping assess an upgrade request and weighing the cost and timeline trade-offs between a full three-phase upgrade and a simpler single-phase addition. I finalised five SMART objectives with my line manager, went out mapping pole and overhead line GPS locations into EMU, and reached out to arrange shadowing with the NGET drone inspection team. I also attended the IET Power Academy conference, taking part in technical talks, workshops, and networking with other engineers.
Week three was more technical. I worked through Company Directives on helicopter inspections and overhead line clearances, completed a Helicopter Inspections CBT, and started both an LTspice transmission line simulation exercise and the Altium Designer PCB course. I learned how pole height and clearance calculations feed into the EMU system, and studied Low Carbon Technology (LCT) connection assessments, including G99/G100 compliance and SGI2/SGI3 generation thresholds. I spent two days on-site with an overhead line team doing pole changes and insulator work, taking part in switching, PME earthing, and helical tie installation, and I learned how ring/loop network topology, back-feeding, and field control handover work. I also requested access to CROWN and STARS and began AutoCAD training.
In week four, I went to Ammanford grid in Swansea, helping apply PCMEs and danger notices, while learning how outage planning and multi-site switching coordination is managed. At Lime Street substation I went through a full protection testing session, covering CT and VT ratio/polarity checks, relay pickup and drop-off testing, distance protection, and overcurrent and earth fault protection, including helping identify a genuine test discrepancy. I also learned ring-main and back-feed theory and cable sizing constraints. Later that week, I helped with an overhead line replacement at Chagford, swapping copper for ABC aluminium cable using a winch and pulley system, and I spent the end of the week preparing my Interim Review.
Week five was my Engineering Design placement. I completed the trainee tasks, using AutoCAD to design a new 33/11kV primary substation, producing layouts and a single-line diagram for "Browns Substation." I learned about transformer isolation and earth fault protection, the difference between isolators and circuit breakers, and how Neutral Earthing Resistors work. I visited Avonbank feeder road and had an in-depth session with a protection engineer covering 11kV distribution protection philosophy: fuse versus earth-type protection, split-ring radial operation, why distance and differential protection aren't used on 11kV or underground circuits, IDMT theory including curve types and grading margins, auto-reclose sequencing, and the differences between electromechanical and digital relays. I finished the week with an overview of the Primary Network Design team and more single-line drawing work for Paulton Sub.
In week six, I continued the Altium PCB course, completing a four-layer stack routing exercise, building a bill of materials, and starting a new custom PCB, while connecting the electronics concepts back to power network principles like interference and transmission-line behaviour. I helped with overhead conductor replacement using winch and brake tensioning, completed my Interim Review, and joined pole inspections with a colleague, learning how pole condition is classified and how clearance and vegetation checks are carried out. I wrote and completed my Protection Engineering report, drawing on everything I'd learned from previous weeks and conversations with protection specialists, sent my protection report to the protection engineer at Avonbank for validation, and had Q&A sessions with colleagues in Innovation and Project Engineering.
Throughout the placement, I've focused on being proactive about my own learning, reaching out to different teams, and building a broad picture of how National Grid's operational, design, and protection functions fit together.